WP5 — Demo plant trials and validation
Lead: Stegra. Duration: M25–M45.
Objectives
- Validate SHINE under industrial conditions
- Develop a real-time Digital Twin
- Analyse long-duration performance and refractory behaviour
- Assess transfer to additional applications
Core tasks
| Task | Activity |
|---|---|
| T5.1 | Definition of demo plant test campaign |
| T5.2 | Digital Twin development for predictive control and performance forecasting |
| T5.3 | Validation of demo plant |
| T5.4 | Post-exposure refractory characterisation |
| T5.5 | Result analysis and lessons learnt |
| T5.6 | Replicability studies in other steel applications |
UPM leads the Digital Twin activity and D5.2, while Stegra leads industrial validation.