SHINE is organised into seven interconnected work packages covering governance, requirements, testing and modelling, industrial deployment, validation, impact and dissemination.

WP1ManageWP2ScenariosWP3Test + modelWP4BuildWP5ValidateWP6ImpactWP7Disseminate
SHINE work-package architecture from project management and scenario definition to industrial validation, impact and dissemination.

Work-package structure

The seven work packages form a connected implementation pathway. WP1 provides governance across the full project; WP2 establishes industrial scenarios and requirements; WP3 generates experimental and modelling knowledge; WP4 delivers the industrial-scale heater; WP5 validates it under industrial conditions; WP6 assesses exploitation and impact; and WP7 supports communication, dissemination, stakeholder engagement, standardisation and skills throughout the project.

WP1

Project management and coordination

Lead: RINA-CSM · M1–M48

Governance, technical coordination, reporting, data management, risk and ethical/legal aspects.

Explore WP1 →

WP2

Definition of reference scenarios

Lead: PIT · M1–M6

Industrial scenarios, use cases, requirements, KPIs and preparation of the small-scale test campaign.

Explore WP2 →

WP3

Preliminary tests and modelling for pilot plant design and development

Lead: RINA-CSM · M4–M21

Pilot testing, refractory development, FEM/CFD modelling, lining life-cycle simulation and carbon-avoidance modelling.

Explore WP3 →

WP4

Electric Heater industrial-scale demo module: design, supply, erection, commissioning

Lead: PIT · M4–M30

Executive engineering, procurement, site preparation, erection and commissioning of the 13.7 MW demonstrator.

Explore WP4 →

WP5

Demo plant trials and validation

Lead: Stegra · M25–M45

Validation campaign, Digital Twin, long-duration industrial trials, refractory assessment and replicability studies.

Explore WP5 →

WP6

Impact assessment and exploitation plan

Lead: RINA-CSM · M19–M48

Market analysis, IPR and exploitation, business models, techno-economic assessment, LCA, LCC and carbon footprint.

Explore WP6 →

WP7

Dissemination, training and synergies with other projects

Lead: UPM · M1–M48

Communication and dissemination, stakeholder engagement, clustering, standardisation, skills analysis and operator training.

Explore WP7 →

Cross-work-package integration

TransitionMain relationship
WP2 → WP3Industrial requirements and KPIs guide pilot testing, refractory studies and modelling.
WP3 → WP4Experimental and numerical evidence supports executive design of the industrial demonstrator.
WP4 → WP5The commissioned heater becomes the basis for the industrial validation campaign.
WP5 → WP6Validated technical evidence feeds replication, market, techno-economic and environmental assessment.
WP1 / WP7 ↔ all WPsManagement, data, communication, exploitation-oriented dissemination and stakeholder engagement operate across the project.