Work Packages
WP4 — Electric Heater industrial-scale demo module: design, supply, erection, commissioning
Lead: PIT. Duration: M4–M30.
Objectives
- Finalise executive design
- Procure heater and BoP components
- Prepare Stegra site
- Install and commission the demonstrator
Core tasks
| Task | Activity |
|---|---|
| T4.1 | Engineering design |
| T4.2 | Purchasing heater |
| T4.3 | Purchasing balance of plant |
| T4.4 | Site preparation and erection |
| T4.5 | Commissioning |